Canada’s Largest Supercharger Site Is Almost Complete!

Ajax, Ontario will soon be home to Canada’s largest Supercharger site, featuring 44 V4 stalls. Construction, which began in May 2025, is now in its final phase. Crews are completing inspections, utility connections, and last-minute site work before the station can officially open.

JML Electric, the contractor responsible for building the site, has been documenting progress on Instagram throughout the year.

Construction Timeline (via JML Electric):

May 29, 2025

June 5, 2025

June 8, 2025

June 20, 2025

August 10, 2025

August 11, 2025

August 13, 2025

August 15, 2025

August 18, 2025

August 20, 2025

August 21, 2025

August 26, 2025

What’s Next

Tesla had previously listed Ajax among the Supercharger sites planned to open in 2025. However, even after construction wraps up, final activation can depend on local utilities, sometimes delaying a launch by several months or more.

Still, if all goes well, the Ajax Supercharger should be operational by the end of 2025.