Construction started in May 2025, and nine months later, the site is still not open. It was supposed to open on January 23, 2026, but has been delayed because of ongoing issues with the local utility provider, Elexicon Energy.
It’s disappointing that despite it being months since we posted about this site nearing completion, it’s still sitting idle.
This is what it looked like then:
This is what it looks like now (photos taken Feb 17, 2026). Site is covered in snow and still fenced up:




We’ve learned a few new things, though. This site is Starlink-connected:

And it will feature multiple accessible parking spots:

Over the winter, on cold days, the older, smaller existing Supercharger nearby was running well beyond capacity. This new site is badly needed, and hopefully, Elexicon Energy can speed things up and finally get it energized.